Total Productive Maintenance (TPM) Implementation Plan on the Topper TNL-85a Machine for Turning Process Effectiveness at PT AMRW
Keywords:
Topper TNL-85a Machine, Fishbone Diagram, Overall Equipment Effectiveness, Six Big Losses, Total Productive MaintenanceAbstract
PT AMRW is a company engaged in the manufacturing industry to produce various sanitation products. One of its departments is the molding department that produces molds, tools, and jigs where the process mostly begins with the turning process using the Topper TNL-85A machine. However, the current machine performance is not optimal due to downtime, not achieving production targets, and delays in product availability so that overtime is required. The three objectives of this study are to determine the value of machine effectiveness using the overall equipment effectiveness (OEE) method, to determine the types of losses that cause machine losses based on the six big losses (SBL), and to provide improvement suggestions to improve the machine's OEE value based on the 8 pillars of total productive maintenance (TPM). Using a descriptive quantitative method, after knowing the losses that occurred, an analysis was carried out to find the root cause using a fishbone diagram before making improvement suggestions. The results of this study found that the machine's OEE value was 73.3% and the SBL was 26.7%. The biggest losses are 11.7% reduction speed losses because the machine has not reached its ideal cycle time, 7% breakdown losses due to machine failures that still occur quite frequently, and 6.8% set-up and adjustment losses due to the setup and adjustment process taking too long. The proposed improvements are based on the eight pillars of TPM, where one root cause uses one of the pillars that best suits the needs.
References
[1] Nurhayani, “Analisis Sektor Industri Manufaktur Di Indonesia,” J. Paradig. Ekon., vol. 17, no. 3, pp. 713–722, 2022.
[2] M. Bilghifary, H. Rachmat, and T. Sjafrizal, “Perancangan User Requirements Specification ( URS ) Sistem Otomasi Terintegrasi Pada Stasiun Exturning , Drilling- Chamfering , Dan Threading Di Pt . Abc Design of User Requirements Specification ( URS ) Integrated Automation System in Exturning , Drillin,” e-Proceeding Eng., vol. 2, no. 2, pp. 3923–3957, 2015.
[3] R. Moonti, H. Uloli, and A. Rasyid, “Analisis Keseimbangan Lintasan Lini Produksi Tepung Kelapa Dengan Metode Ranked Positional Weight Dan Region Approach,” Jambura Ind. Rev., vol. 2, no. 1, pp. 1–10, 2022, doi: 10.37905/jirev.2.1.01-10.
[4] N. C. Dewi and D. I. Rinawati, “Analisis Penerapan Total Productive Maintenance (TPM) Dengan Perhitungan Overall Equipment Efectiveness (OEE) Dan Six Big Losses Mesin Cavitec PT. Essentra Surabaya,” Ind. Eng. Online J., vol. 4, no. 4, 2015.
[5] N. Hairiyah, R. R. Amalia, and R. A. Wijaya, “Analisis Total Productive Maintenance (TPM) Pada Stasiun Kernel Crushing Plant (KCP) Di PT. X,” J. Teknol. Pertan. Andalas, vol. 23, no. 1, pp. 101–110, 2019, doi: 10.25077/jtpa.23.1.103-110.2019.
[6] T. B. Agung, M. Imtihan, and S. Nugroho, “Usulan Perbaikan Melalui Penerapan Total Productive Maintenance Dengan Metode OEE Pada Mesin Twin Screw Extruder PVC Di PT. XYZ,” TEKNOSAINS J. Sains, Teknol. dan Inform., vol. 8, no. 1, pp. 10–22, 2021, doi: 10.37373/tekno.v8i1.78.
[7] J. Gianfranco, M. I. Taufik, F. Hariadi, and M. Fauzi, “Pengukuran Total Productive Maintenance (TPM) Menggunakan Metode Overall Equipment Effectiveness (OEE) Pada Mesin Reaktor Produksi,” J. Lebesgue J. Ilm. Pendidik. Mat. Mat. dan Stat., vol. 3, no. 1, pp. 160–172, 2022, doi: 10.46306/lb.v3i1.109.
[8] R. Baety, E. Budiasih, and F. T. D. Atmaji, “Penerapan Total Productive Maintenace (TPM) Dalam Bottleneck Auto-Part Machining Line Menggunakan Metode Overall Equipment Effectiveness (OEE),” e-Proceeding Eng., vol. 6, no. 2, pp. 6496–6505, 2019.
[9] G. Muhaemin and A. E. Nugraha, “Penerapan Total Productive Maintenance (TPM) Pada Perawatan Mesin Cutter di PT. XYZ,” J. Ilm. Wahana Pendidik., vol. 8, no. 9, pp. 205–219, 2022, doi: 10.5281/zenodo.6645451.
[10] Musyafa’ah and A. Sofiana, “Analysis of Total Productive Maintenance (TPM) Application Using Overall Equipment Effectiveness (OEE) and Six Big Losses on Disamatic Machine PT . XYZ,” OPSI J. Optimasi Sist. Ind., vol. 15, no. 1, pp. 56–63, 2022, doi: 10.31315/opsi.v15i1.6630.
[11] R. Wahyudi, R. G. Ferdana, and A. T. Nugraha, “Penerapan Metode Overall Equipment Effectiveness (OEE) Dan Six Big Losses Untuk Mengukur Efektivitas Mesin Packing Pada PT Surya Tsabat Mandiri,” J. Optim., vol. 09, no. 02, pp. 82–89, 2023, doi: https://doi.org/10.35308/jopt.v9i2.
[12] E. Aminah and L. Theresia, “Penerapan Teknik Kaizen Untuk Total Productive Maintenance (TPM) di Perusahaan Manufaktur,” Technopex, pp. 212–219, 2018.
[13] M. F. Ardiansyah and E. P. Widjajati, “Penjadwalan Preventive Maintenance Pada Mesin Mixing Dalam Produksi Brick Batu Tahan Api Dengan Menggunakan Metode Age Replacement Pada PT XYZ,” Juminten, vol. 2, no. 1, pp. 144–155, 2021, doi: 10.33005/juminten.v2i1.219.
[14] A. S. Ludwika, “Penerapan Total Productive Maintenance Menggunakan Overall Equipment Effectiveness (Oee) Dan Six Big Losses Untuk Mengevaluasi Efektivitas Mesin (Studi Kasus Pada PT Subah Spinning Mills),” Universitas Islam Indonesia, 2021.
[15] D. . Stamatis, The OEE Primer: Understanding Overall Equipment Effectiveness, Reliability, And Maintainability. New York: CRC Press, 2010.
[16] R. A. Perwira, R. Wahyudi, and A. T. Nugraha, “Analisis Efektivitas Rotary Car Dumper (RCD) 3 dengan Metode Overall Equipment Effectiveness (OEE): Studi Kasus pada PT Bukit Asam Unit Pelabuhan Tarahan,” J. Integr., vol. 16, no. 1, pp. 48–57, 2024, doi: https://doi.org/10.30871/ji.v16i1.6675.
[17] N. C. Dewi and D. I. Rinawati, “Analisis Penerapan Total Productive Maintenance (TPM) Dengan Perhitungan Overall Equipment Effectiveness (OEE) Dan Six Big Losses Mesin Cavitex PT. Essentra Surabaya,” Ind. Eng. Online J., vol. 4, no. 4, 2015.
[18] T. Facchinetti and G. Citterio, “Application Of The Overall Equipment Effectiveness To A Service Company,” IEEE Access, vol. 10, pp. 106613–106640, 2022, doi: 10.1109/ACCESS.2022.3211266.
[19] M. D. Al-Azmi, J. Alhilman, and A. Pamoso, “Usulan Perancangan Formulit Pemeliharaan Mesin Duan KWEI di PT XYZ Menggunakan Metode Total Productive Maintenance (TPM) dan Overall Equipment Effectiveness (OEE),” e-Proceeding Eng., vol. 10, no. 3, pp. 3025–3034, 2023.
[20] K. R. Ngoy and K. Israel, “The Strategy of Successful Total Productive Maintenance ( TPM ): Implementation and Benefits of TPM ( Literature Review ),” IJIRMPS, vol. 9, no. 6, pp. 43–52, 2021.
[21] F. Kurniawan, M. I. H. Umam, and I. Kusumanto, “Optimalisasi Penerapan Total Productive Maintenance Pada Mesin Mosher I Dengan Metode Overall Equipment Effectiveness,” J. Teknol. dan Manaj. Ind. Terap., vol. 4, no. I, pp. 1–9, 2025, doi: 10.55826/jtmit.v4ii.526.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Jurnal Media Teknik dan Sistem Industri

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.