Production Line Efficiency Improvement Using the Line Balancing Method on the 3W Frame Welding Line at PT X

Authors

  • Mohamad Zulfahmi Politeknik Astra
  • Yuliani Fauziah Astra Polytechnic
  • Filemondra Damanik PT Dharma Polimetal Tbk

DOI:

https://doi.org/10.35194/jmtsi.v10i2.6581

Keywords:

Line Balancing

Abstract

Manufacturing assembly lines frequently face operational inefficiencies due to unbalanced workloads and discrepancies between legacy Work Instructions (WI) and actual shop-floor cycle times. At PT X, the 3W Frame Welding Line exhibited a low initial Line Efficiency (LE) of 54,83% and a 3,290-second time data gap between documented procedures and actual operations, resulting in severe line imbalances and restricted output. This study aims to eliminate the time data discrepancy, redesign the workload allocation across workstations within the target takt time, and evaluate the resulting operational and financial improvements. The methodology integrates the Eight Steps problem-solving framework with the Ranked Positional Weight (RPW) heuristic method and Lean visualization tools, including Standardized Work Combination Tables (SWCT), Standardized Work Charts (SWC), and Yamazumi Charts based on stopwatch time studies. The results show that standardization successfully eliminated the 3,290-second data gap with 100% document accuracy. Following line balancing across three workstations, LE increased significantly from 54,83% to 94.67%, Balance Delay (BD) dropped from 45.17% to 5.33%, and daily production capacity doubled from 10 to 20 units without overtime. This study concludes that combining the RPW method with visual standardized work effectively resolves shop-floor bottlenecks and data asynchrony, delivering a projected Net Quality Income (NQI) of IDR 4,596,249,600 per year.

Author Biographies

Mohamad Zulfahmi , Politeknik Astra

Department of Production and Manufacturing Process Engineering

Filemondra Damanik, PT Dharma Polimetal Tbk

Manufacturing 3-Wheel Department

References

[1] R. S. Aji and P. E. Widjajanti, “Line Balancing Analysis Using Ranked Positional Weight and Region Approach Method in Nail Production,” J. LA MULTIAPP, vol. 05, no. 03, pp. 232–244, 2024, doi: 10.37899/journallamultiapp.v5i3.1361.

[2] M. Bajomo, A. Ogbeyemi, and W. Hang, “A Systems Dynamics Approach to the Management of Material Procurement for Engineering, Procurement and Construction industry, International Journal of Production Economics,” J. Prod. Econ., vol. 244, 2022, doi: https://doi.org/10.1016/j.ijpe.2021.108390.

[3] F. Achmadi, B. Harsanto, and A. Yunani, “Improvement of Assembly Manufacturing Process through Value Stream Mapping and Ranked Positional Weight : An Empirical Evidence from the Defense Industry,” 2023, doi: https://doi.org/10.3390/pr11051334.

[4] P. Asih, “Pengukuran Efisiensi Waktu Proses Produksi Pada Setiap Stasiun Kerja Pembuatan Keramik Model Guci Ukuran Tinggi 80 cm . ( Studi Kasus Pada Home Industri Jaya Ceramik Yogyakarta ),” J. Rekayasa Ind., vol. 3, no. 1, pp. 41–50, 2021, doi: https://doi.org/10.37631/jri.v3i1.290.

[5] M. R. Rahmantto and E. P. Widjajati, “Line Balancing Analysis Using Ranked Positional Weight and Region Approach Methods on Broad Plate Production Line,” J. LA MULTIAPP, vol. 06, no. 01, 2025, doi: 10.37899/journallamultiapp.v6i1.1767.

[6] É. L. Luciano, M. T. Okano, R. B. Ribeiro, T. C. F. Rocha, and W. A. D. Chaves, Implementation of Takt Time in the Development of a New Value Stream Mapping in the Production of Coffee Powder. Springer International Publishing, 2021. doi: 10.1007/978-3-030-78570-3.

[7] I. Purnamasari and A. S. Cahyana, “LINE BALANCING DENGAN METODE RANKED POSITION WEIGHT (RPW),” Spektrum Ind., vol. 13, no. 2, pp. 115–228, 2015, doi: https://doi.org/10.12928/si.v13i2.2693.

[8] A. B. Sulistyo, “PERENCANAAN LINE BALANCING PROSES PRODUKSI PADA SHEARING LINE PLANT DENGAN MENGGUNAKAN METODE RANK POSITION WEIGHT,” J. Penelit. dan Apl. Sist. dan Tek. Ind., vol. XVI, no. 1, pp. 49–60, 2022, doi: https://doi.org/10.22441/pasti.2022.v16i1.005.

[9] M. Afifuddin, “PENERAPAN LINE BALANCING MENGGUNAKAN METODE RANKED POSITION WEIGHT (RPW) UNTUK MENINGKATKAN OUTPUT PRODUKSI PADA HOME INDUSTRI PEMBUATAN SEPATU BOLA,” J. Ind. Eng. Manag., vol. 4, no. 1, pp. 40–48, 2019, doi: http://dx.doi.org/10.33536/jiem.v4i1.287.

[10] H. Chang, R. M. Silitonga, Y. Zelita, A. Muna, and Y.-T. Jou, “Application of Ranked Position Weight and Region Approach Method in Overcoming Bottlenecks in Garment Industry,” Res. Synerg. Found., vol. 2, no. 1, pp. 23–36, 2022, doi: https://doi.org/10.31098/cset.v2i1.512.

[11] D. Siregar and A. Yasid, “ANALISIS PENINGKATAN KAPASITAS PRODUKSI PADA PROSES PEMBUATAN FRAME MOTOR KLX DENGAN METODE LINE BALANCING DI PT . KMI,” J. Matrik, vol. XIX, no. 1, pp. 37–48, 2018, doi: 10.30587/matrik.v19i1.580.

[12] Supriyono, D. Suryanto, F. Hendra, and R. Efendi, “LINE BALANCING ANALYSIS BY USED RANK POSITIONAL WEIGHT ( RPW ) ( CASE STUDY : PART BODY S11038Z PROCESS ),” J. Ilm. Tek. Mesin, vol. 14, no. 2, pp. 123–129, 2020, doi: 10.24853/sintek.14.2.123-129.

[13] G. Campilho, P. Ferreira, T. Santos, P. Dias, and G. Silva, “Assembly and Improvement of an Assembly Line in the Automotive Industry,” Procedia Manuf., vol. 38, no. 2019, pp. 1444–1452, 2020, doi: 10.1016/j.promfg.2020.01.143.

[14] A. Mortada and A. Soulhi, “Improvement of Assembly Line Efficiency by Using Lean Manufacturing Tools and Line Balancing Techniques,” Adv. Sci. Technol. Res. J., vol. 17, no. 4, pp. 89–109, 2023, doi: https://doi.org/10.12913/22998624/169257.

[15] M. Al Farizi, C. D. Maulana, and J. Purnama, “PENGARUH TIME AND MOTION STUDY TERHADAP PROSES SETTING UNTUK MENINGKATKAN PRODUKTIVITAS DIVISI HPS (Studi kasus PT. XYZ),” vol. 3, no. September, pp. 22–30, 2023.

[16] M. Fitri, M. Yetrina, Susriyanti, and S. Laurenza, “Optimalisasi Line Balancing Menggunakan Metode Ranked Positional Weight, Moodie Young, dan J-Wagon,” J. Teknol., vol. 13, pp. 74–80, 2023, doi: 10.35134/jitekin.v13i1.103.

[17] H. Chen, P. Wang, and Q. Ji, “Analysis of the Application Effect of PDCA Cycle Management Combined With Risk Factor Management Nursing for Reducing Infection Rate in Operating Room,” vol. 9, no. March, pp. 1–7, 2022, doi: 10.3389/fsurg.2022.837014.

[18] D. Sjarifudin and H. Kurnia, “The PDCA Approach with Seven Quality Tools for Quality Improvement Men ’ s Formal Jackets in Indonesia Garment Industry,” vol. 24, no. 2, pp. 159–176, 2022, doi: 10.32734/jsti.v24i2.7711.

[19] I. K. Sriwana, A. Jatikusumo, N. Erni, A. Suwandi, and T. Rachman, “Usulan Perbaikan Keseimbangan Lini di PT . XYZ Menggunakan Moodie-Young dan Ranked Positional Weight untuk Meningkatkan Efisiensi Lini Produksi,” J. Metris, vol. 22, pp. 82–91, 2021.