Optimalisasi Waktu Pelaksanaan Proyek Konstruksi Rumah Tinggal Menggunakan Metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique)

MS Adhiarsya Perdana, Rianita Puspa Sari

Abstract


CV. Sinar Ciloa Rahayu is a company engaged in construction. One of the projects handled by CV. Sinar Ciloa Rahayu is a residential construction project located at Perumahan Gombong Permai, Cianjur, West Java. The implementation of the residential construction project was delayed from the predetermined schedule, which was 99 days, the delay was due to the less than optimal management of the company. To overcome delays in project execution time requires good planning, scheduling, and control. The purpose of this research is to optimize the project execution time, so that the project can be completed according to a predetermined schedule. The optimization process will be carried out using the Critical Path Method (CPM) which will result in optimal scheduling and using the Project Evaluation and Review Technique (PERT) method which will produce probability of project completion time. The results obtained are the project has accelerated by 13 days with a project completion time of 99 days to 86 days with a probability of 93.65%.

 

CV. Sinar Ciloa Rahayu merupakan sebuah perusahaan yang bergerak dibidang konstruksi. Salah satu proyek yang dijalankan oleh CV. Sinar Ciloa Rahayu adalah proyek pembangunan konstruksi rumah tinggal yang berlokasi di Perumahan Gombong Permai Cianjur, Jawa Barat. Pelaksanaan proyek pembangunan konstruksi rumah tinggal tersebut mengalami keterlambatan dari jadwal yang telah ditentukan yaitu 99 hari, keterlambatan tesebut disebabkan karena kurang optimalnya manajemen perusahaan. Untuk mengatasi keterlambatan waktu pengerjaan proyek dibutuhkan perencanaan, penjadwalan, dan pengendalian yang baik. Tujuan penelitian ini adalah untuk mengoptimalkan waktu pelaksanaan proyek, sehingga proyek tersebut dapat selesai sesuai dengan jadwal yang telah ditetapkan. Proses optimalisasi tersebut menggunakan metode Critical Path Method (CPM) yang akan menghasilkan penjadwalan yang optimal dan metode Program Evaluation and Review Technique (PERT) digunakan untuk menghasilkan probabilitas waktu penyelesaian proyek. Hasil yang diperoleh adalah proyek mengalami percepatan sebesar 13 hari dengan waktu penyelesaian proyek dari 99 hari menjadi 86 hari dengan probabilitas sebesar 93,65%.


Keywords


Project Management; CPM; PERT; Optimization Process; Project Evaluation; scheduling

Full Text:

PDF

References


W. Agyei, “Project Planning And Scheduling Using PERT And CPM Techniques With Linear Programming Case Study,†Int. J. Sci. Technol. Res., vol. 4, no. 8, pp. 222–227, 2015.

J. Heizer and B. Render, Operations Management 12th Edition. Pearson, 2011.

T. I. Julkarnaen and L. Herlina, “Analisa Perbaikan Penjadwalan Perakitan Panel Listrik Dengan Metode CPM dan PERT ( Studi Kasus : PT . Mega Karya Engineering ),†J. Tek. Ind. Untirta, 2015.

G. P. Arianie and N. B. Puspitasari, “Perencanaan Manajemen Proyek dalam Meningkatkan Efisiensi dan Efektifitas Sumber Daya Perusahaan (Studi Kasus : Qiscus Pte Ltd) Project Management Planning in Increasing the Efficiency and Effectiveness of Company Resources (Case Study: Qiscus Pte Ltd),†J@ti Undip J. Tek. Ind., vol. 12, no. 3, p. 189, 2017.

S. Basriati and A. Melda, “Analisis Biaya Pembangunan Proyek Perumahan Menggunakan Metode PERT dan EVM (Studi Kasus: Perumahan D’Lion Cluster),†Semin. Nas. Teknol. Inf. Komun. dan Ind., pp. 642–647, 2017.

M. Irfan, “Sistem Manajemen Proyek Perumahan Menggunakan Metode Pert-Cpm,†Soliter, vol. 1, pp. 135–145, 2018, [Online]. Available: https://www.soliter.ulm.ac.id/index.php/soliter/article/download/30/27.

M. Mazlum and A. F. Güneri, “CPM, PERT and Project Management with Fuzzy Logic Technique and Implementation on a Business,†Procedia - Soc. Behav. Sci., vol. 210, pp. 348–357, 2015, doi: 10.1016/j.sbspro.2015.11.378.

N. M. E. Wardani, S. Musdalifah, and D. Lusiyanti, “Optimalisasi Biaya Dan Waktu Pelaksanaan Proyek Pembangunan Perumahan Citraland Palu Menggunakan Metode Program Evaluation and Review Technique (Pert) – Critical Path Method (Cpm),†J. Ilm. Mat. Dan Terap., vol. 15, no. 2, pp. 197–208, 2018, doi: 10.22487/2540766x.2018.v15.i2.11353.

S. Sofiyanurriyanti and N. H. Ningsih, “Optimalisasi Proses Produksi H-Beam Dengan Metode Pert (Program Evalution Review Technique) Dan Cpm (Critical Path Method) Di Pt. Mulcindo Steel Industry,†KAIZEN Manag. Syst. Ind. Eng. J., vol. 2, no. 2, p. 59, 2019, doi: 10.25273/kaizen.v2i2.5971.

J. Oka and D. Kartikasari, “Evaluasi Manajemen Waktu Proyek Menggunakan Metode Pert Dan Cpm Pada Pengerjaan ‘Proyek Reparasi Crane Lampson’ Di Pt Mcdermott Indonesia,†J. Appl. Bus. Adm., vol. 1, no. 1, pp. 28–36, 2019, doi: 10.30871/jaba.v1i1.1257.

W. W. D. dan P. Banjarnahor, “Analisis Pelaksanaan Proyek Perumahan dengan Metode CPM (Critical Path Method) Dan PERT (Project Evaluation And Review Technique) (Studi Kasus Proyek Perumahan Citra Turi),†Pelita Inform., vol. 17 Nomor 1, pp. 108–113, 2018, [Online]. Available: Citra Turi, Pembangunan Perumahan,PERT-CPM%0AJurnal Pelita Informatika.

A. Angelin and S. Ariayanti, “ANALISIS PENJADWALAN PROYEK NEW PRODUCT DEVELOPMENT MENGGUNAKAN METODE PERT DAN CPM,†J. Ilm. Tek. Ind., vol. 6, no. 1, pp. 63–70, 2018.

H. A. Taha, Introduction to Operational Research 8th.pdf, 8th ed. New Jersey: Pearson, 2007.

A. Nalhadi and N. Suntana, “Analisa Infrastruktur Desa Sukaci-Baros Dengan Metode Critical Path Method ( CPM ),†J. Sist. dan Manaj. Ind., vol. 1, no. 1, pp. 35–42, 2017.

H. Dimyati and K. Nurjaman, Manajemen Proyek. Bandung: Pustaka Setia, 2014.

I. O. Priska, S. El Unas, and K. Rahayu, “ANALISIS DURASI PEKERJAAN TANGGA PANEL BERDASARKAN METODE PERT DAN CCPM (Studi Kasus: Proyek Ruko The Boulevard Jakarta Garden City),†J. Mhs. Jur. Tek. Sipil, vol. 1, 2017.




DOI: https://doi.org/10.35194/jmtsi.v6i2.1944

Refbacks

  • There are currently no refbacks.


This Journal is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Media Teknik dan Sistem Industri ISSN: 2581-0561 (online); 2581-0529 (cetak).


Gedung Fakultas Teknik UNSUR Jl. Pasir Gede Raya, Cianjur, Jawa Barat 43216| Telp./Fax. (0263) 283578 |E-mail: jmtsi@unsur.ac.id 

JMTSI (Jurnal Media Teknik dan Sistem Industri) INDEXED BY :